Two Styles on One Line at the Same Time: The Modular Line and the Line Schedule

KEY POINTS
Small-lot, high-mix sewing factories in Korea often run several styles on one line in the same period, and a schedule board that draws one bar per line cannot show this. A modular line splits the people on a line into modules that each sew a garment from start to finish, so one line runs two or more styles at once, and the schedule has to split the line into lanes to track each style’s dates and daily target separately.
One line, one style
On a mass-production line, the schedule board gives each line one row and draws each order on it as a single bar from start date to finish date. The next style’s bar starts only when the earlier style finishes, so a line carries one style at a time.

For a line running orders of several thousand pieces for weeks at a time, this works. Load the next style on the day the earlier one finishes and keep the bars back to back so the line never sits empty.
Where several styles run on one line
Sewing factories in Korea work differently. A Korean shirt factory with a workforce of twenty-some operators, where SIJE ran a field validation in 2025, changed styles every 1 to 2 days and ran several styles on a single line.1
In Korean sewing shops each operator handles 3 to 10 operations, so the line leader splits the line’s operators as orders come in and runs two styles on the same day.2 Assigning a whole line to one small order leaves people idle, and waiting for the earlier style to finish pushes back the delivery date.
We covered this factory in Why Smart Factory Systems Did Not Fit Small Sewing Factories.
The modular line
A modular line splits the people on a line into small modules, and operators move between several operations within the module so that each module sews a garment from start to finish. Sources on sewing production systems put a module at 4 to 17 people and the operations per operator at 2 to 4. The workstations are usually set in a U, with more workstations than operators, and operators move between them.3

Because each module completes a garment, the modules on one line can take different styles, and that is how one line runs two or more styles in the same period. This is why the modular approach is regarded as suited to small orders and frequent style changes,4 and a large Korean apparel OEM also runs modular production with product-specific layouts at its overseas knit factories, separate from its conventional lines, and supplies with no minimum order quantity.5

This only works when operators can handle several operations. On a line where each operator does just one operation, splitting the people leaves operations uncovered, but on a line with operators who move across operations, every operation for both styles stays covered after the split. In return, training operators across operations costs money, and the line needs more workstations than operators.3
What one bar cannot show
Put a modular line on a conventional schedule board and there is no place to draw the second style running in the same period. The board shows the line as full with one style, so it cannot tell you when the second style finishes or whether the line has people to spare.
With no place on the board, putting the second style on it means finding an empty line, and the small order then waits until a line frees up or slips behind the earlier style and misses its delivery date.

Two lanes in one line
The Monolis schedule shows a line split into lanes. Move another style onto a running line and the line splits into two lanes, with the original style in the upper lane and the moved style in the lower lane, side by side on the same dates.
Each style has its own card, so the production planner checks quantity, start date and EX-FAC (ex-factory date) margin style by style and sees two styles running on one line in a single schedule view. A small order goes straight into one lane of a running line instead of taking a whole line.
Numbers per lane
Once a line is split into lanes, the numbers have to be read per lane.
The daily target comes from the SMV on the operation breakdown, the number of operators and the factory efficiency. Splitting a line’s people across two styles cuts the operators in each lane, so the daily target is reset to each lane’s headcount.
The learning curve also starts again from day 1 for each style. A style moved into a lane produces less than its daily target on the first day and reaches the target over several days, so production days have to be calculated separately from the lane’s daily target and the learning curve. We covered that calculation in Why Order Quantity Divided by the Daily Target Is Not the Production Days.
Summary
| Item | One line, one style | Modular line |
|---|---|---|
| Styles in progress | One at a time | Two or more in the same period |
| Small orders | Wait for an empty line or for the earlier style to finish | Go straight into a lane on a running line |
| Operators | Can run with one operation each | Requires operators who handle several operations |
| Schedule view | One bar per line | Lanes within the line, one bar per style |
| Daily target | Based on line headcount | Based on lane headcount |
Sewing factories in Korea already run several styles on one line. When the schedule shows that operation as it is, the production planner sees the spare people on a line and each style’s delivery date in the same view.
Related: Why Smart Factory Systems Did Not Fit Small Sewing Factories
References
- SIJE internal data, results of a 2025 field validation. Style change cycle and line operation. ↩
- SIJE internal data, summary of how sewing shops in Korea are organized. Operations per operator, high-mix, low-volume production. ↩
- Textile Study Center, Modular Production System. Module size (4 to 17 people), operations per operator (2 to 4), more workstations than operators in a U-shaped layout, cost of multi-skill training, suited to small orders and frequent style changes. ↩
- Gartex India, How Modular Manufacturing Is Transforming Apparel SMEs in India. Module size (4 to 20 people), multi-skilled operators, small high-mix orders and several styles running at once. ↩
- Business overview on the website of a large Korean apparel OEM. Modular production at overseas knit factories, product-specific layouts, supply with no minimum order quantity. ↩
