What ‘One Car Every Minute’ Means: From Ford’s Moving Assembly Line to Takt on the Sewing Line

Mid-century illustration of the 1913 flywheel magneto assembly line at Ford's Highland Park plant, with workers lined up along a long bench
The flywheel magneto assembly line at Highland Park in 1913. The job one man used to do was split into 29 operations, and the workers stood in a row along the line.

This is the third post in our manufacturing history series, following part 1 on the Gilbreths’ motion study and part 2 on Sakichi Toyoda’s automatic loom.

KEY POINTS

In April 1913, Ford put magneto assembly on a moving line at the Highland Park plant. Instead of workers walking to find parts, the work came to the workers, and Ford changed the line speed between 60 and 18 inches per minute to find a pace every worker could keep. Labour time for one chassis fell from 12 hours 28 minutes to 1 hour 33 minutes. The Takt Time on a sewing operation breakdown is this same pace. A sewing line, however, has no conveyor to set the pace, so the pace has to be measured and shown on screen before the line can be balanced.

When people hear that “a car comes off the line every minute,” it is easy to take it to mean that a car is built in one minute. That is not what it means. It means that every operation on the line finishes its own share of the work within one minute. Only then does each car move forward one position every minute, and only then does one car come out at the end every minute.

On a sewing operation breakdown, that one minute is the number we call Takt. In this post we go back to the Highland Park plant in Detroit in 1913, where this pace first entered a factory, and then look at why the same pace is so hard to see on a sewing line.

An idea from the overhead rails of a meatpacking plant

Before Ford, car factories built a car in one fixed spot. Workers walked around the car to find parts and tools as they assembled it. In his 1922 autobiography Henry Ford wrote that the undirected worker spends more of his time walking about for materials and tools than he does in working.1

Ford reversed the direction. Instead of the man going to the work, the work came to the man.1 The idea came from the meatpacking plants of Chicago, where carcasses hung from an overhead rail moved past workers who each stayed in place and did only their own part. Ford brought this method into car assembly.1

Ford summed up his principles of assembly in three points: place tools and men in the sequence of the operation so that each part travels the least distance; have each worker drop a finished part in the same place every time so it passes to the next man; and use moving assembly lines to deliver parts within easy reach.1 Where the Gilbreths tried to cut motions, Ford tried to cut steps.

From 20 minutes to 5: the magneto line

The first experiment was the flywheel magneto, which makes the spark for the engine. It happened around April 1, 1913.12 Before that, one worker assembled a magneto from start to finish, turning out 35 to 40 in a nine-hour day, or about 20 minutes each.1

Ford split this job into 29 operations laid out in a row along the line. Assembly time fell to 13 minutes 10 seconds. In 1914 the line was raised eight inches and the time fell to 7 minutes, and further adjustment of the line speed brought it down to 5 minutes.1

None of this worked out as quickly as it sounds. The line speed had to be tried out step by step. The first speed, 60 inches per minute, was too fast, and 18 inches per minute was too slow. Ford settled on 44 inches per minute.1 When a line is too fast, the magneto passes before the worker can finish; when it is too slow, the worker finishes and waits for the next one.

Ford put the principle this way: a man must have every second necessary but not a single unnecessary second.1 The line speed was the pace every worker had to keep, and Ford set that pace with the line rather than with the hands of the workers.

One chassis, from 12 hours 28 minutes to 1 hour 33 minutes

With the result proven on the magneto, Ford extended the method to the motor and the chassis. Motor assembly was divided into 84 operations. In October 1913 assembling one motor took 9 hours 54 minutes of labour; six months later it took 5 hours 56 minutes.1

The chassis is the frame of the car. The best record for stationary chassis assembly was an average of 12 hours 28 minutes per chassis. Ford had the chassis drawn with a rope and windlass down a line 250 feet long, while six assemblers travelled with it and picked up parts from piles along the way. This rough experiment alone cut the time to 5 hours 50 minutes.1

Mid-century illustration of Model T chassis moving along a floor line at Ford's Highland Park plant
The chassis assembly line at Highland Park. The chassis moves along the floor line while workers stay in place and fit the parts.

In early 1914 the line was raised to waist height, with one line at 26¾ inches and another at 24½ inches to suit squads of different heights. Dividing the work further so that each man made fewer movements brought the labour time per chassis down to 1 hour 33 minutes.1

Mid-century illustration of a car body being lowered down a ramp onto a chassis beside the Highland Park plant
At Highland Park, a body sent down from the upper floor is lowered onto a chassis.

The pace set by the line, and the price people paid

The line was fast, but people did not stay. The work meant repeating the same motion all day at the speed of the line. In early 1914 Ford had 14,000 employees, and to keep that force it had to hire at the rate of about 53,000 people a year.1

On January 5, 1914, Ford announced that it would pay five dollars a day.3 The working day was cut to eight hours.1 Strictly speaking it was a profit-sharing plan added to the existing wage. A worker who earned $2.30 a day, for example, kept that base pay and received $2.70 more, but only if he met the living conditions the company set.3 The effect was large. In 1915 Ford had to hire only 6,508 people, and most of those were taken on because the business was growing.1

The line also changed the price. The Model T touring car sold 18,664 units at $950 in 1909~10 and 785,432 units at $360 in 1916~17.1 About 15 million Model Ts were built in all.2

Takt: the time limit every operation must keep

On a sewing operation breakdown, the pace Ford found with his line speed is called Takt Time. Takt is German for beat. It is the time limit every operation must keep so that the line flows without stopping.

You calculate it by dividing the time available in a day by the daily target. The example screen in How to Read an Operation Breakdown divides 28,800 seconds by a daily target of 603 pieces to get a Takt of 48 seconds (example data). 28,800 seconds is eight hours expressed in seconds, and the eight-hour day is also the standard Ford brought into his plant in 1914.

Once Takt is set, each operation’s standard time (SMV) is compared with it. An operation whose SMV is longer than Takt cannot keep the pace with one person, so more people are added; short operations are combined so that one person covers two. Fitting the time of every operation within Takt is called line balancing. Why people are added in steps of 0.5 is covered in What Man Power 0.5 Means.

A sewing line without a conveyor

On Ford’s line, the machine set the pace. When the line moved at 44 inches per minute, workers had to follow that speed, and anyone falling behind was visible at once: a magneto that left a worker’s hands unfinished showed up right there.

A sewing line is different. On many sewing lines the work is tied in bundles and passed by hand. Each operator takes the bundle from the person before, sews their own operation and passes it on. Because nothing forces the pace, every operator works at a different speed, and the differences are not visible right away. When one operation runs a little slower than Takt, bundles start to pile up in front of it, and the bottleneck shows only once the pile is big enough to notice.

Bundles of cut fabric tied with string piled on a sewing table
Bundles piling up in front of an operation are a sign that the operation is not keeping Takt.

On top of that, the pace of a sewing line changes every day. When a new style comes in, output stays below target until the operators’ hands get used to the work, and it rises day by day along the learning curve. The SMV on the operation breakdown stays the same, but the actual working time on the floor differs from day to day.

Making the pace of a sewing line visible

Ford forced the pace with a conveyor. On a sewing line the pace has to be measured and shown instead. SIJE’s Monolog counts work cycles at each sewing machine, compares the measured time of each operation with Takt Time and finds the operations that exceed Takt. It calculates in advance which operation will become a bottleneck if the current speed continues, and suggests actions such as moving people one to four hours before the problem appears.4

The line balancing simulation in SIJE’s solution overlays the measured time of each operation on the Takt baseline to find the bottleneck, and immediately calculates how the line changes when someone is moved to another operation. It also recommends the number of people and the seating layout.5 The production manager decides which option to use.

A supervisor checking operation status on a tablet in front of a sewing line
The manager looks at the measured time of each operation against Takt in front of the line and decides where to move people.

Wrapping up

What Ford worked hardest to get right in 1913 was not the conveyor but the pace of the line. Moving between 60 and 18 inches per minute, he found a speed every worker could keep, and that speed set the output of the whole line. A sewing line runs on the same kind of pace. But there is no machine to set it, so the line only becomes visible when you measure how many seconds each operation actually takes and put that next to Takt.

Glossary

  • Moving assembly line: a method where the item being assembled moves along a line and each worker stays in place doing only their own part of the work.
  • Flywheel magneto: a generator attached to the engine flywheel of the Model T that produces the electricity for ignition.
  • Chassis: the frame of a car that carries the engine, wheels and axles.
  • Takt Time: the time limit every operation must keep so that the line flows without stopping, found by dividing the time available in a day by the daily target.
  • SMV (Standard Minute Value): the standard time it takes to perform one operation once.
  • Line balancing: fitting the time of every operation within Takt by adding people to some operations and combining others.
  • Bundle: a set quantity of cut pieces tied together. On a sewing line, work passes to the next operation bundle by bundle.
  • Bottleneck: the slowest operation on the line. Work in progress piles up in front of it, and it sets the speed of the whole line.

👉 How to Read an Operation Breakdown: Operations, SMV, Takt, Man Power
👉 What Man Power 0.5 Means: Three Ways to Break a Bottleneck
👉 Why Order Quantity Divided by the Daily Target Is Not the Production Days: The Learning Curve and the Line Schedule
👉 The Couple Who Put Light Bulbs on Workers’ Fingers: From the Gilbreths’ Motion Study to Sewing SMV

References

  1. Henry Ford and Samuel Crowther, My Life and Work (1922), Project Gutenberg Taking the work to the men and the three principles of assembly, the overhead trolley of the Chicago packers, the magneto line around April 1, 1913 (about 20 minutes, 29 operations, 13 minutes 10 seconds, raised eight inches in 1914 to 7 minutes, then 5 minutes), line speeds of 60, 18 and 44 inches per minute, the motor in 84 operations and from 9 hours 54 minutes to 5 hours 56 minutes, the chassis at 12 hours 28 minutes, the 250-foot rope experiment and 5 hours 50 minutes, lines at 26¾ and 24½ inches and 1 hour 33 minutes, 14,000 employees and about 53,000 hires a year, five dollars a day and the eight-hour day effective January 12, 1914, 6,508 hires in 1915, touring car prices and production by year. ↩
  2. The Henry Ford, “Ford Methods and the Ford Shops” The moving magneto line around April 1, 1913, about 15 million Model Ts. ↩
  3. The Henry Ford, “Ford’s Five-Dollar Day” Announcement on January 5, 1914, the profit-sharing plan, the extra $2.70 for a worker earning $2.30, eligibility conditions and home inspections. ↩
  4. SIJE website, Monolog Detecting operations that exceed Takt Time and suggesting staff reassignment one to four hours before a problem. ↩
  5. SIJE website, Products Line balancing simulation: comparing measured time per operation with the Takt baseline, calculating the effect of moving people, Auto Layout recommending headcount and seating. ↩